I-80 Will – Advance. Rebuild. Transform

I-80 WILL – SCHEDULE

Over 16 miles of I-80 from Minooka to New Lenox will be reconstructed, including over 30 bridges. Construction will be implemented in phases to minimize impacts on traffic. 

Construction is underway and anticipated to be substantially completed in 2028.

COMPLETED

A. HOUBOLT ROAD EXTENSION

A joint project with Joliet, Will County, and CenterPoint Properties

B. U.S. 30 INTERCHANGE IMPROVEMENTS

This includes I-80 reconstruction and added lanes between U.S. 30 and Gougar Road

C. HOUBOLT ROAD DIVERGING DIAMOND INTERCHANGE CONVERSION

D. BRIDGES AT HICKORY CREEK, RICHARDS STREET, ROWELL AVENUE/CANADIAN NATIONAL RAILROAD

F. SHEPLEY ROAD OVER I-80 BRIDGE REPLACEMENT

G. WHEELER AVENUE OVER I-80 BRIDGE REPLACEMENT

H. BRIGGS STREET OVER I-80 BRIDGE REPLACEMENT

I. RIVER ROAD OVER I-80 BRIDGE REPLACEMENT

 
UNDER CONSTRUCTION

E. I-80: RIDGE ROAD TO RIVER ROAD RECONSTRUCTION

Projected Time Frame: 2025 Completion

J. I-80: RIVER ROAD TO WHEELER AVENUE RECONSTRUCTION

This includes I-55 and Larkin Avenue Interchange reconstruction

Projected Time Frame: 2026 Completion

K. I-80: ROWELL AVENUE TO GOUGAR ROAD RECONSTRUCTION

This includes Briggs Street roadway & interchange reconstruction

Projected Time Frame: 2025 Completion

L. RICHARDS STREET RECONSTRUCTION

5th Avenue to Colburn Avenue

Projected Time Frame: 2024-2025

 
2025-2026 CONSTRUCTION

N. I-55 INTERCHANGE

Projected Time Frame: Winter 2024 – Fall 2026

O. LARKIN INTERCHANGE

Projected Time Frame: Spring 2025 – Fall 2026

 

2026-2028 CONSTRUCTION

M. I-80: DES PLAINES RIVER BRIDGE REPLACEMENT

This includes Center Street and Chicago Street Interchange reconstruction. Phase Three construction is dependent on completion of land acquisition activities.

Projected Time Frame: 2026-2028

 

Note: Substantial completion with all lanes open on I-80 is planned for November 2028. Construction activities such as the demolition of the existing Des Plaines River bridges will continue into 2029.